ISRO Mechanical & Aerospace 2018 - Question 50

All ISRO Mechanical & Aerospace papers | ISRO Mechanical & Aerospace 2018

Topic: Industrial Engineering

PERT has following time estimate

  • A. one time estimate
  • B. two time estimate
  • C. three time estimate
  • D. nil time estimate

Answer: C. three time estimate

Explanation: PERT uses three time estimates: Optimistic time estimate, Pessimistic time estimate, and Most likely time estimate.