Topic: Industrial Engineering
PERT has following time estimate
- A. one time estimate
- B. two time estimate
- C. three time estimate
- D. nil time estimate
Answer: C. three time estimate
Explanation: PERT uses three time estimates: Optimistic time estimate, Pessimistic time estimate, and Most likely time estimate.