ISRO Mechanical & Aerospace 2008 - Question 25

All ISRO Mechanical & Aerospace papers | ISRO Mechanical & Aerospace 2008

Topic: Industrial Engineering

The following data pertain to a worker: base rate = Rs. 20 per hour, Time taken for completing the job = 2 hours, Standard time = 3 hours. Under Halsey plan the total earning of the worker is

  • A. Rs. 36.67
  • B. Rs. 40.67
  • C. Rs. 46.67
  • D. Rs. 56.57

Answer: C. Rs. 46.67

Explanation: Under the Halsey plan, E = R*Ta + (Time saved / Standard time) * R * (Ts - Ta). Here time saved = 3 - 2 = 1 hr. E = (20 * 2) + (1/3) * 20 * (3 - 2) = 40 + 6.67 = 46.67 Rs.