ISRO Electrical Engineering (EE) 2013 - Question 51

All ISRO Electrical Engineering (EE) papers | ISRO Electrical Engineering (EE) 2013

Grounding is generally done in transmission line at

  • A. The supply end
  • B. The receiving end
  • C. Middle of the line
  • D. Anywhere

Answer: A. The supply end

Explanation: Neutral grounding is generally done at the supply end (generating station/substation).