Topic: Software Engineering
As per the Capability Maturity Model (CMM), the process maturity levels are defined as
Level 1: Initial
Level 2: (A)
Level 3: (B)
Level 4: (C)
Level 5: Optimizing
Identify (A), (B) and (C).
- A. A: Defined, B: Repeatable, C: Managed
- B. A: Repeatable, B: Managed, C: Defined
- C. A: Repeatable, B: Defined, C: Managed
- D. A: Defined, B: Managed, C: Repeatable
Answer: C. A: Repeatable, B: Defined, C: Managed
Explanation: The 5 maturity levels of the Capability Maturity Model (CMM) are: 1 - Initial, 2 - Repeatable, 3 - Defined, 4 - Managed, 5 - Optimizing. Therefore, A = Repeatable, B = Defined, and C = Managed.