In a construction site, the RMC vehicle arrived two hours late with 7 m^3 of concrete. As a site engineer, what will be your action?
- A. Allow the vehicle for concreting
- B. Make arrangement to add more cement and allow concreting
- C. Stop the vehicle, Reject the batch and inform the competent authority
- D. Send the concrete to other site