Operations Research - ISRO Mechanical & Aerospace Subject-Wise PYQ Practice

Practice topic-wise Operations Research previous year questions for ISRO Mechanical & Aerospace with instant step-by-step solutions and formula breakdowns.

All ISRO Mechanical & Aerospace papers

11 questions.

Question 1

Year: 2008 | Topic: Industrial Engineering

The following data pertain to a worker: base rate = Rs. 20 per hour, Time taken for completing the job = 2 hours, Standard time = 3 hours. Under Halsey plan the total earning of the worker is

  • A. Rs. 36.67
  • B. Rs. 40.67
  • C. Rs. 46.67
  • D. Rs. 56.57

Answer: C. Rs. 46.67

Explanation: Under the Halsey plan, E = R*Ta + (Time saved / Standard time) * R * (Ts - Ta). Here time saved = 3 - 2 = 1 hr. E = (20 * 2) + (1/3) * 20 * (3 - 2) = 40 + 6.67 = 46.67 Rs.

Question 2

Year: 2017 | Topic: Industrial Engineering

A statistical process control chart which shows the number of defects found in a subgroup of fixed size is

  • A. C-chart
  • B. R-chart
  • C. Control chart
  • D. Gantt chart

Answer: A. C-chart

Explanation: A C-chart is an attributes control chart used for monitoring the number of defects per unit when the sample size is fixed.

Question 3

Year: 2017 | Topic: Industrial Engineering

In process charts, the symbol used for inspection is

  • A. A circle
  • B. A square
  • C. An arrow
  • D. A triangle

Answer: B. A square

Explanation: In process flow charts, a square symbol represents an inspection step, where an object is checked for its quality or quantity.

Question 4

Year: 2017 | Topic: Industrial Engineering

Transportation method is concerned with

  • A. Value analysis
  • B. Linear programming
  • C. Queuing theory
  • D. Break-even analysis

Answer: B. Linear programming

Explanation: The transportation problem is a classic application of linear programming, used to find the most efficient routes to transport goods from sources to destinations.

Question 5

Year: 2017 | Topic: Industrial Engineering

In dynamic balancing of machines, which of the following is NOT a method of measuring the magnitude and location of correction weight for a two plane correction?

  • A. Pivoted cradle method
  • B. Mechanical compensation method
  • C. Pivoted compensation method
  • D. Nodal point method

Answer: C. Pivoted compensation method

Explanation: Pivoted compensation method is not a standard recognized method for dynamic balancing. The other three are established techniques.

Question 6

Year: 2017 | Topic: Industrial Engineering

Adaptive response rate forecasting is related to

  • A. Production Planning
  • B. Production Scheduling
  • C. Value analysis
  • D. Inventory control

Answer: D. Inventory control

Explanation: Adaptive response rate forecasting is a technique for estimating demand in inventory control systems, particularly for items with changing demand patterns.

Question 7

Year: 2017 | Topic: Industrial Engineering

Fredric W Taylor introduced a system of working known as

  • A. line organization
  • B. effective organization
  • C. functional organization
  • D. none of the above

Answer: C. functional organization

Explanation: F.W. Taylor, the father of scientific management, advocated for functional organization, where workers receive orders from several different specialist supervisors, each with expertise in a specific area.

Question 8

Year: 2018 | Topic: Industrial Engineering

PERT has following time estimate

  • A. one time estimate
  • B. two time estimate
  • C. three time estimate
  • D. nil time estimate

Answer: C. three time estimate

Explanation: PERT uses three time estimates: Optimistic time estimate, Pessimistic time estimate, and Most likely time estimate.

Question 9

Year: 2024 | Topic: Industrial Engineering

A manufacturer has the following data regarding a product. Fixed cost per month = Rs.80,000, Variable cost per unit = Rs.350, Selling price per unit = Rs.500, Production capacity = 1600 units per month. If the production is carried out at 75% of the rated capacity, then monthly profit is (in Rs.)

  • A. 1 Lakh
  • B. 1.2 Lakhs
  • C. 1.4 Lakhs
  • D. 0.8 Lakhs

Answer: A. 1 Lakh

Explanation: Actual units produced = $0.75 * 1600 = 1200$ units. Total revenue = $1200 * 500 = 6,00,000$ Rs. Total cost = Fixed Cost + (Variable Cost * Units) = $80,000 + (350 * 1200) = 80,000 + 4,20,000 = 5,00,000$ Rs. Monthly profit = Total Revenue - Total Cost = $6,00,000 - 5,00,000 = 1,00,000$ Rs (1 Lakh).

Question 10

Year: 2024 | Topic: Industrial Engineering

For a PERT activity, the optimistic time is 6 minutes, the most likely time is 9 minutes and pessimistic time is 16 minutes. The expected time of the activity (in seconds) is

  • A. 600
  • B. 540
  • C. 620
  • D. 580

Answer: D. 580

Explanation: Expected time $T_e = (t_o + 4t_m + t_p) / 6 = (6 + 4(9) + 16) / 6 = (6 + 36 + 16) / 6 = 58 / 6$ minutes. Converting to seconds: $(58 / 6) * 60 = 58 * 10 = 580$ seconds.

Question 11

Year: 2024 | Topic: Industrial Engineering

For a particular project, six activities are to be carried out. The precedence relation and duration of activities are as per the following table. The minimum project completion time (in days) is (A=6, B follows A=5, C follows A=8, D follows B=11, E follows C=6, F follows D,E=7)

  • A. 32
  • B. 27
  • C. 29
  • D. 30

Answer: C. 29

Explanation: There are two paths to completion in the network network: Path 1 is A -> B -> D -> F which takes 6 + 5 + 11 + 7 = 29 days. Path 2 is A -> C -> E -> F which takes 6 + 8 + 6 + 7 = 27 days. The minimum project completion time is dictated by the critical (longest) path, which is 29 days.