ISRO Electrical Engineering (EE) 2023 - Question 29

All ISRO Electrical Engineering (EE) papers | ISRO Electrical Engineering (EE) 2023

A power station has a maximum demand of 15000 kW. The annual load factor is 50% and the plant capacity factor is 40%. The reserve capacity of the plant is

  • A. 5630 kW
  • B. 4210 kW
  • C. 3750 kW
  • D. 2760 kW

Answer: C. 3750 kW

Explanation: Average load = 15000 × 0.50 = 7500 kW. Plant capacity = 7500 / 0.40 = 18750 kW. Reserve capacity = 18750 - 15000 = 3750 kW.