ISRO Electrical Engineering (EE) 2020 - Question 79

All ISRO Electrical Engineering (EE) papers | ISRO Electrical Engineering (EE) 2020

A 100 MW power station delivers 100 MW for 2 hours, 50 MW for 6 hours in a day and is shut down for maintenance for 45 days each year. Calculate its annual load factor?

  • A. 20%
  • B. 21%
  • C. 22.5%
  • D. 18.3%

| | All questions of ISRO Electrical Engineering (EE) 2020