A 100 MW power station delivers 100 MW for 2 hours, 50 MW for 6 hours in a day and is shut down for maintenance for 45 days each year. Calculate its annual load factor?
- A. 20%
- B. 21%
- C. 22.5%
- D. 18.3%
All ISRO Electrical Engineering (EE) papers | ISRO Electrical Engineering (EE) 2020
A 100 MW power station delivers 100 MW for 2 hours, 50 MW for 6 hours in a day and is shut down for maintenance for 45 days each year. Calculate its annual load factor?
Previous question | Next question | All questions of ISRO Electrical Engineering (EE) 2020