ISRO Electrical Engineering (EE) 2013 - Question 28

All ISRO Electrical Engineering (EE) papers | ISRO Electrical Engineering (EE) 2013

Non loading heat run test on transformers is performed by means of -

  • A. SC test.
  • B. OC test.
  • C. Half time on SC and half time on OC.
  • D. Sumpner's test.

Answer: D. Sumpner's test.

Explanation: Sumpner's (back-to-back) test loads both transformers thermally with only the losses drawn from the supply (heat run test).