GATE ME Scheduling: Previous Year Questions

GATE ME (Mechanical Engineering) Scheduling previous year questions from Industrial Engineering, with figures and the answer key.

Industrial Engineering | All GATE ME papers

GATE ME 2026, Question 35 (2 marks, MCQ)

Industrial Engineering - Scheduling

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below. Job Due date Work remaining (in days) M N O P Which job(s) has/have critical ratio less than unity?

GATE ME 2026 question 35

  1. Job O and Job P
  2. Job P
  3. Job M and Job N
  4. Job N and Job O

Answer: D

GATE ME 2024, Question 34 (1 mark, MCQ)

Industrial Engineering - Scheduling

A set of jobs arrive at time to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below. The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is

GATE ME 2024 question 34

  1. W-X-Z-V-Y-U
  2. W-X-V-Z-Y-U
  3. W-U-Z-V-Y-X
  4. U-Y-V-Z-X-W

GATE ME 2022 Set 2, Question 41 (2 marks, MCQ)

Industrial Engineering - Scheduling

Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

GATE ME 2022 Set 2 question 41

  1. 31
  2. 33
  3. 30
  4. 32

Answer: B

GATE ME 2021 Set 1, Question 38 (2 marks, MCQ)

Industrial Engineering - Scheduling

Q.28 A set of jobs A,B,C,D,E,F,G,Harrive at time = for rocessingon turning and grinding machines. Each job needs to be processed in sequence -first on the turning machine and second on the grinding machine,and the grindingmustoccurimmediatelyafterturning.Theprocessingtimesofthe jobs are given below. Job A B C D E F G H Turning 2 4 8 9 7 6 5 10 (minutes) Grinding (minutes) If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is (A) A-E-D-F-H-C-G-B (B) A-D-E-F-H-C-G-B (C) G-E-D-F-H-C-A-B (D) B-G-C-H-F-D-E-A

GATE ME 2021 Set 1 question 38

Answer: A

GATE ME 2018 Set 1, Question 62 (2 marks, NAT)

Industrial Engineering - Scheduling

Q.52 Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is ___________ (correct to two decimal places). Job Processing time (days) Due date (days) A 3 8 B 7 16 C 4 4 D 9 18 E 5 17 F 13 19

GATE ME 2018 Set 1 question 62

Answer: 6.31 to 6.35

GATE ME 2017 Set 1, Question 31 (2 marks, NAT)

Industrial Engineering - Scheduling

Following data refers to the jobs which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days.

GATE ME 2017 Set 1 question 31

Answer: 31

GATE ME 2010, Question 5 (2 marks, MCQ)

Industrial Engineering - Scheduling

Four jobs are to be processed on a machine as per data listed in the table. If the Earliest Due Date rule is used to sequence the jobs, the number of jobs delayed is

GATE ME 2010 question 5

Answer: C

GATE ME 2010, Question 6 (2 marks, MCQ)

Industrial Engineering - Scheduling

Four jobs are to be processed on a machine as per data listed in the table. Using the Shortest Processing Time rule, total tardiness is

GATE ME 2010 question 6

Answer: D

GATE ME 2009, Question 7 (2 marks, MCQ)

Industrial Engineering - Scheduling

Six jobs arrived in a sequence as given below: Average flow time (in days) for the above jobs using Shortest Processing Time rule is

GATE ME 2009 question 7

Answer: A

GATE ME 2008, Question 8 (2 marks, MCQ)

Industrial Engineering - Scheduling

A set of jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. per day. A schedule that minimizes the total inventory cost is

GATE ME 2008 question 8

Answer: A

GATE ME 1998, Question 9 (5 marks, NAT)

Industrial Engineering - Scheduling

A job shop has orders to be completed by a single turning center. The processing times and due dates are as follows: Assume that all orders are ready for processing. Give a production schedule that minimizes the average flow time. Compare this schedule with one that minimizes tardiness (lateness).

GATE ME 1998 question 9

GATE ME 1996, Question 10 (5 marks, TEXT)

Industrial Engineering - Scheduling

A job shop incurs a cost of Rs./- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data: Which schedule will minimize the total cost? What is the minimum total cost? Which jobs (if any) fail to meet their due dates?

GATE ME 1996 question 10

GATE ME 1990, Question 11 (5 marks, TEXT)

Industrial Engineering - Scheduling

Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.

GATE ME 1990 question 11

Answer: Shortest time rule is better