GATE ME Production Planning and Control: Previous Year Questions
GATE ME (Mechanical Engineering) Production Planning and Control previous year questions from Industrial Engineering, with figures and the answer key.
Industrial Engineering | All GATE ME papers
GATE ME 2023, Question 55 (2 marks, NAT)
Industrial Engineering - Production Planning and Control
A solid part (see figure) of polymer material is to be fabricated by additive manufacturing (AM) in square-shaped layers starting from the bottom of the part working upwards. The nozzle diameter of the AM machine is a/10 mm and the nozzle follows a linear serpentine path parallel to the sides of the square layers with a feed rate of a/5 mm/min. Ignore any tool path motions other than those involved in adding material, and any other delays between layers or the serpentine scan lines. The time taken to fabricate this part is ___________ minutes. (Answer in integer)

Answer: 11458 to 11461
GATE ME 2022 Set 1, Question 59 (2 marks, NAT)
Industrial Engineering - Production Planning and Control
The product structure diagram shows the number of different components required at each level to produce one unit of the final product P. If there are 50 units of on hand inventory of component A, the number of additional units of component A needed to produce 10 units of product P is _________ (in integer).

Answer: 110
GATE ME 2020 Set 1, Question 43 (2 marks, MCQ)
Industrial Engineering - Production Planning and Control
Q.No.33 For anassemblyline,theproductionratewas4piecesperhour and the average processing time was 60minutes.TheWIPinventorywas calculated.Now,the production rate iskept the same,and the averageprocessing time is brought down by 30percent.Asa result of this change in the processing time,theWIP inventory (A) decreasesby25% increases by25% (B) (C) decreasesby30% (D) increasesby30%

Answer: C
GATE ME 2020 Set 2, Question 23 (1 mark, MCQ)
Industrial Engineering - Production Planning and Control
Q.No.13 InMaterialsRequirementPlanning,if theinventoryholdingcostisveryhighand thesetupcostiszero,which oneof thefollowinglot sizing approaches should be oposn (A) EconomicOrderQuantity (B) Lot-for-Lot (C) BaseStock Level (D) FixedPeriodQuantity,for2periods

Answer: B
GATE ME 2015 Set 2, Question 65 (2 marks, NAT)
Industrial Engineering - Production Planning and Control
A manufacturer has the following data regarding a product: Fixed cost per month Rs. Variable cost per unit Rs. Selling price per unit Rs. Production capacity units per month If the production is carried out at of the rated capacity, then the monthly profit (in Rs.) is ______________

Answer: 68000 to 72000
GATE ME 2014 Set 2, Question 29 (1 mark, MCQ)
Industrial Engineering - Production Planning and Control
A component can be produced by any of the four processes and . The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of pieces is

Answer: B
GATE ME 2012, Question 2 (1 mark, MCQ)
Industrial Engineering - Production Planning and Control
Which one of the following is NOT a decision taken during the aggregate production planning stage?
- Scheduling of machines
- Amount of labour to be committed
- Rate at which production should happen
- Inventory to be carried forward
Answer: A
GATE ME 2007, Question 8 (2 marks, MCQ)
Industrial Engineering - Production Planning and Control
Capacities of production of an item over consecutive months in regular time are and and in overtime are and The demands over those months are and The cost of production in regular time and overtime are respectively Rs. per item and Rs. per item. Inventory carrying cost is Rs. per item per month. The levels of starting and final inventory are nil. Backorder is not permitted. For minimum cost of plan, the level of planned production in overtime in the third month is

Answer: B
GATE ME 2001, Question 3 (1 mark, MSQ)
Industrial Engineering - Production Planning and Control
Production flow analysis is a method of identifying part families that uses data from

- engineering drawings
- production schedule
- bill of materials
- route sheets
Answer: B, C
GATE ME 2000, Question 10 (5 marks, TEXT)
Industrial Engineering - Production Planning and Control
The forecasts for a product for the next three months are given as and units. The number of regular time days and overtime days available are and respectively. With the existing number of employees, the company can produce units per day. To meet the high demand in the third month, the company decides to hire people to increase the daily production to units. The following costs are given : Cost of regular time production Rs. per unit Cost of overtime production Rs. Per unit Cost of hiring where is the increase in daily capacity Inventory Rs. per unit per month (based on average inventory) Shortage (back-ordering cost) Rs. per unit per month The beginning inventory is units. The company decides to produce and units respectively in the three months. Compute the cost of the production plan.

GATE ME 1995, Question 4 (1 mark, MCQ)
Industrial Engineering - Production Planning and Control
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
Answer: D
GATE ME 1995, Question 9 (2 marks, TEXT)
Industrial Engineering - Production Planning and Control