GATE ME Pert and Cpm: Previous Year Questions

GATE ME (Mechanical Engineering) Pert and Cpm previous year questions from Industrial Engineering, with figures and the answer key.

Industrial Engineering | All GATE ME papers

GATE ME 2026, Question 38 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic , most likely , and pessimistic are given in the table below. The expected project length is weeks (in integer).

GATE ME 2026 question 38

Answer: 22

GATE ME 2025, Question 65 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is __________hours (answer in integer). Activity Immediate predecessor Duration(hours)

GATE ME 2025 question 65

Answer: 2

GATE ME 2022 Set 1, Question 42 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ______ hours. Activity Time (hours) Immediate predecessors A B C D A E B F B G C H D, E I F J G K H, I, J

GATE ME 2022 Set 1 question 42

  1. 5
  2. 10
  3. 8
  4. 9

Answer: B

GATE ME 2022 Set 2, Question 59 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).

GATE ME 2022 Set 2 question 59

Answer: 15

GATE ME 2021 Set 1, Question 45 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

Q.35 Activities A,B,C andD form the critical pathfor a projectwith a PERT network.Themeans andvariances of the activitydurationfor eachactivity aregiven below.Allactivity durations follow the Gaussian (normal) distribution,and are independent of each other. Activity A B C D Mean (days) 6 11 8 15 Variance 4 4 9 (days) The probability that the project will be completed within 40 days is (round off to two decimal places). (Note: Probability is a number between 0 and 1).

GATE ME 2021 Set 1 question 45

Answer: 0.5

GATE ME 2021 Set 2, Question 18 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

Q.8 APERTnetworkhas9activitieson itscriticalpath.Thestandard deviation of each activity on the critical path is 3.The standard deviation of the critical path is (A) 3 (B) 6 (C) 27 (D) 81

GATE ME 2021 Set 2 question 18

Answer: B

GATE ME 2020 Set 1, Question 23 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

Q.No.13 Crash Cost-Normal Cost (A) Crash Time Normal Cost (B) Crash Time-Normal Time (C) Crash Cost CrashTime-Normal Time (D) Crash Cost-Normal Cost Normal Time-CrashTime

GATE ME 2020 Set 1 question 23

Answer: D

GATE ME 2020 Set 2, Question 33 (1 mark, NAT)

Industrial Engineering - Pert and Cpm

Q.No.23 Consider the followingnetwork ofactivities,witheach activity namedA-L, illustratedinthenodesofthenetwork. START FINISH The number of hoursrequiredfor each activityis shown alongside thenodes.The slackon theactivityL,is hours.

GATE ME 2020 Set 2 question 33

Answer: 2

GATE ME 2019 Set 1, Question 65 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

Q.55 estimated duration is also provided in the table below: Activity Immediatepredecessor Estimated duration (weeks) P 5 Q 1 R Q 2 S P, R 4 T P 6 U S, T 3 If all activities other than S take the estimated amount of time, the maximum duration (in weeks)of the activity S without delaying the completion of the project is

GATE ME 2019 Set 1 question 65

Answer: 6

GATE ME 2019 Set 2, Question 45 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Q.35 The activities of aproject,their duration and theprecedencerelationshipsaregiven inthe table. For example, in a precedence relationship “X < Y, Z" means that X is predecessor of activitiesYand Z.Thetime tocomplete theactivitiesalongthecriticalpathis weeks. Activity Duration (Weeks) Precedence Relationship A 5 A<B, C,D B 7 B<E,F,G C 10 C<I D 6 D<G E 3 E<H F 9 F<I G 7 G<I H 4 H<I I 2 (A) 17 (B)21 (C) 23 (D) 25

GATE ME 2019 Set 2 question 45

Answer: C

GATE ME 2018 Set 2, Question 61 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

Q.51 The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is _______.

GATE ME 2018 Set 2 question 61

Answer: 7 or 11

GATE ME 2017 Set 2, Question 24 (1 mark, NAT)

Industrial Engineering - Pert and Cpm

The standard deviation of linear dimensions and are and , respectively. When assembled, the standard deviation (in ) of the following linear dimension is ___________.

GATE ME 2017 Set 2 question 24

Answer: 5

GATE ME 2017 Set 2, Question 49 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project starts with activity and ends with activity The precedence relation and durations of the activities are as per the following table: The minimum project completion time (in days) is ___________

GATE ME 2017 Set 2 question 49

Answer: 30

GATE ME 2016 Set 2, Question 65 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project consists of activities, to . The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node is _____________

GATE ME 2016 Set 2 question 65

Answer: 14

GATE ME 2016 Set 3, Question 35 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

In chart, the activity time distribution is

GATE ME 2016 Set 3 question 35

  1. Normal
  2. Binomial
  3. Poisson
  4. Beta

Answer: D

GATE ME 2015 Set 1, Question 43 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Following data refers to the activities of a project, where, node refers to the start and node refers to the end of the project. The critical path in the network is

GATE ME 2015 Set 1 question 43

Answer: B

GATE ME 2015 Set 2, Question 64 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project consists of activities. The network along with the time durations (in days) for various activities is shown in the figure. The minimum time (in days) for completion of the project is _____________

GATE ME 2015 Set 2 question 64

Answer: 39 to 40

GATE ME 2014, Question 3 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

A minimal spanning tree in network flow models involves

  1. all the nodes with cycle/loop allowed
  2. all the nodes with cycle/loop not allowed
  3. shortest path between start and end nodes
  4. all the nodes with directed arcs

Answer: B

GATE ME 2014 Set 2, Question 60 (2 marks, NAT)

Industrial Engineering - Pert and Cpm

A project has four activities and as shown below. The normal cost of the project is Rs. and the overhead cost is Rs. per day. If the project duration has to be crashed down to days, the total cost (in Rupees) of the project is ______________.

GATE ME 2014 Set 2 question 60

Answer: 12490 to 12510

GATE ME 2014 Set 3, Question 31 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

Q.21 A minimal spanning tree in network flow models involves (A) all the nodes with cycle/loop allowed (B) all the nodes with cycle/loop not allowed (C) shortest path between start and end nodes (D) all the nodes with directed arcs ME03 (GATE 2014)

GATE ME 2014 Set 3 question 31

Answer: B

GATE ME 2014 Set 3, Question 60 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Consider the given project network, where numbers along various activities represent the normal time. The free float on activity - and the project duration, respectively, are

GATE ME 2014 Set 3 question 60

Answer: A

GATE ME 2014 Set 4, Question 60 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities and respectively, are

GATE ME 2014 Set 4 question 60

  1. and
  2. and
  3. and
  4. and

Answer: B

GATE ME 2012, Question 19 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. The critical path for the project is

GATE ME 2012 question 19

Answer: C

GATE ME 2012, Question 20 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. If the duration of activity alone is changed from to days, then the

GATE ME 2012 question 20

  1. critical path remains the same and the total duration to complete the project changes to days.
  2. critical path and the total duration to complete the project remains the same.
  3. critical path changes but the total duration to complete the project remains the same.
  4. critical path changes and the total duration to complete the project changes to days.

Answer: A

GATE ME 2010, Question 21 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

The project activities, precedence relationships and durations are described in the table. The critical path of the project is

GATE ME 2010 question 21

Answer: D

GATE ME 2009, Question 4 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

The expected time of a activity in terms of optimistic time , pessimistic and most likely time is given by

GATE ME 2009 question 4

Answer: A

GATE ME 2009, Question 22 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Consider the following network The optimistic time, most likely time and pessimistic time of all the activities are given in the table The critical path duration of the network (in days) is

GATE ME 2009 question 22

Answer: D

GATE ME 2009, Question 23 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Consider the following network The optimistic time, most likely time and pessimistic time of all the activities are given in the table The standard deviation of the critical path is

GATE ME 2009 question 23

Answer: C

GATE ME 2008, Question 24 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

For the network below, the objective is to find the length of the shortest path from node to node Let be the length of directed are from node to node . Let be the length of the shortest path from to node Which of the following equations can be used to find ?

GATE ME 2008 question 24

Answer: C

GATE ME 2006, Question 25 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Consider a network for a project involving six tasks ( to ) The expected completion time of the project is

GATE ME 2006 question 25

  1. days
  2. days
  3. days
  4. days

Answer: D

GATE ME 2006, Question 26 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

Consider a network for a project involving six tasks ( to ) The standard deviation of the critical path of the project is

GATE ME 2006 question 26

  1. days
  2. days
  3. days
  4. days

Answer: A

GATE ME 2005, Question 27 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

A project has six activities to with respective activity durations days. The network has three paths and All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by day is

GATE ME 2005 question 27

Answer: C

GATE ME 2004, Question 5 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

In analysis a critical activity has

GATE ME 2004 question 5

  1. maximum Float
  2. zero Float
  3. maximum Cost
  4. minimum Cost

Answer: B

GATE ME 2003, Question 28 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

A project consists of activities to shown in the net in the following figure with the duration of the activities marked in days. The project can be completed

GATE ME 2003 question 28

  1. between day
  2. between days
  3. between days
  4. between days

Answer: C

GATE ME 2002, Question 29 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

A project consists of three parallel paths with mean durations and variances of and respectively. According to the standard assumptions, the distribution of the project duration is

GATE ME 2002 question 29

  1. Beta with mean and standard deviation
  2. Beta with mean and standard deviation
  3. Normal with mean and standard deviation
  4. Normal with mean and standard deviation

Answer: D

GATE ME 2002, Question 31 (5 marks, NAT)

Industrial Engineering - Pert and Cpm

The precedence relations and durations of jobs in a project are given below: (a) Draw the activity-on-arc project network (b) Determine all critical path(s) and their duration(s). (c) What is the total float for jobs and

GATE ME 2002 question 31

GATE ME 2000, Question 32 (5 marks, NAT)

Industrial Engineering - Pert and Cpm

Given below are the data for a project network. (a) Draw the network for the above project capturing the precedence relationships. (b) Find the critical path and its duration.

GATE ME 2000 question 32

GATE ME 1997, Question 6 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

A dummy activity is used in network to describe

GATE ME 1997 question 6

  1. Precedence relationship
  2. Necessary time delay
  3. Resource restriction
  4. Resource idleness

Answer: A

GATE ME 1997, Question 33 (5 marks, TEXT)

Industrial Engineering - Pert and Cpm

A project plan is given below: (a) Construct a network (b) Find the critical path and estimate the project duration.

GATE ME 1997 question 33

GATE ME 1995, Question 7 (1 mark, MCQ)

Industrial Engineering - Pert and Cpm

In the distribution of activity times is assumed to be

GATE ME 1995 question 7

  1. Normal
  2. Gamma
  3. Beta
  4. Exponential

Answer: C

GATE ME 1995, Question 34 (5 marks, NAT)

Industrial Engineering - Pert and Cpm

A project with the following data is to be implemented: (a) What is the minimum duration of the project? (b) Draw a Gantt chart for the early schedule (c) Determine the peak requirement of money and the day on which it occurs in above schedule.

GATE ME 1995 question 34

GATE ME 1993, Question 35 (5 marks, NAT)

Industrial Engineering - Pert and Cpm

For a small project with five jobs, the following data is given (i) Draw the project network in activity on arc mode (ii) Under assumptions, determine the distribution of project duration.

GATE ME 1993 question 35

GATE ME 1990, Question 30 (2 marks, MCQ)

Industrial Engineering - Pert and Cpm

In the construction of networks, dummy activities are introduced in order to :

  1. Compute the slack on all events
  2. Transfer resources, if necessary, during monitoring
  3. Clearly designate a precedence relationship
  4. Simplify the crashing plan

Answer: C