GATE ME 2026, Question 34 (2 marks, MCQ)
Industrial Engineering - Linear Programming
An objective function of primal variables ( and ) is described below: Minimize is the objective function of the dual of . and represent the corresponding dual variables. Which one of the following options represents the correct form of ?

- Maximize Subject to
- Maximize Subject to
- Maximize Subject to
- Maximize Subject to
Answer: C
GATE ME 2024, Question 39 (2 marks, MCQ)
Industrial Engineering - Linear Programming
At the current basic feasible solution (bfs) , the simplex method yields the following form of a linear programming problem in standard form: minimize s.t. Here the objective function is written as a function of the non-basic variables. If the simplex method moves to the adjacent bfs that best improves the objective function, which of the following represents the objective function at , assuming that the objective function is written in the same manner as above?

Answer: A
GATE ME 2023, Question 14 (1 mark, MCQ)
Industrial Engineering - Linear Programming
Which one of the options given represents the feasible region of the linear programming model: Maximize 45X$_{1}$ + 60X$_{2}$ X$_{1}$≤ 45 X$_{2}$≤ 50 10X$_{1}$ + 10X$_{2}$≥ 600 25X$_{1}$ + 5X$_{2}$≤ 750

- Region P
- Region Q
- Region R
- Region S
Answer: B
GATE ME 2022 Set 1, Question 21 (1 mark, MCQ)
Industrial Engineering - Linear Programming
In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource is
- positive
- negative
- zero
- infinity
Answer: C
GATE ME 2022 Set 2, Question 42 (2 marks, MCQ)
Industrial Engineering - Linear Programming
A manufacturing unit produces two products Pl and P2. For each piece of P1 and P2, the table below provides quantities of materials M1, M2, and M3 required, and also the profit earned. The maximum quantity available per day for M1, M2 and M3 is also provided. The maximum possible profit per day is ₹ ______

- 5000
- 4000
- 3000
- 6000
Answer: B
GATE ME 2021 Set 2, Question 39 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Q.29 A factory produces m(i =1,2,..,m) products,each of which requires processing on n (j = 1,2,..,n) workstations. Let ai; be the amount of processing time that one unit of the ith product requires on the jth workstation. Let therevenue from selling one unit of theithproductbe r;and hbe the holding cost per unit per time period for the ith product.The planning horizon consists of T (t = 1, 2, ..,T) time periods. The minimum demand that must be satisfied in time period t is dit,and the capacity of the jthworkstation in time period t is Cjt. Consider the aggregate planning formulation below, with decision variables Sit (amount of product i sold in time period t), Xit (amount of product i manufactured in time period t) and It (amount of product i held

Answer: A
GATE ME 2020 Set 1, Question 57 (2 marks, NAT)
Industrial Engineering - Linear Programming
Q.No.47 TwobusinessownersShvetaandAshokruntheirbusinessesintwodifferent states.Eachofthem,independentoftheother,producestwoproductsAandB, sells them at Rs.2,000 perkg and Rs.3,000 perkg,respectively,and usesLinear ProgrammingtodeterminetheoptimalquantityofAandBtomaximize their respective daily revenue.Their constraints are as follows:i)for each business owner,the production process is such that the daily production of A has to be at least as much as B, and the upper limit for production of B is 10 kg per day,and ii)therespectivestateregulationsrestrictShveta’sproductionofAtoless than 20kgper day,and Ashok's production of A to less than 15kg per day.The demandof bothA andBinboth the statesisveryhigh andeverythingproduced is sold. The absolutevalueofthedifferenceindaily(optimal)revenue ofShveta and Ashokis thousand Rupees(roundoff to2 decimal places).

Answer: 9.9 to 10.1
GATE ME 2018 Set 1, Question 61 (2 marks, NAT)
Industrial Engineering - Linear Programming
Q.51 The minimum value of 3𝑥+ 5𝑦 such that: 3𝑥+ 5𝑦≤15 4𝑥+ 9𝑦≤8 13𝑥+ 2𝑦≤ 2 𝑥≥0, 𝑦≥0 is _______.

Answer: 0
GATE ME 2018 Set 2, Question 45 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Q.35 The problem of maximizing z x x subject to constraints x x 10, x 0, x 0 1 2 1 2 1 2 and x 5 has 2 (A) no solution (B) one solution (C) two solutions (D) more than two solutions

Answer: B
GATE ME 2017 Set 1, Question 30 (2 marks, NAT)
Industrial Engineering - Linear Programming
Two models, and of a product earn profits of Rs. and Rs. per piece, respectively. Production times for and are hours and hours, respectively, while the total production time available is hours. For a total batch size of to maximize profit, the number of units of to be produced is ____________.

Answer: 15
GATE ME 2017 Set 2, Question 51 (2 marks, NAT)
Industrial Engineering - Linear Programming
Maximize Subject to In the starting simplex tableau, and are non-basic variables and the value of is zero. The value of in the next simplex tableau is __________________.

Answer: 40
GATE ME 2016 Set 1, Question 65 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Maximize Subject to The above linear programming problem has

- infeasible solution
- unbounded solution
- alternative optimum solutions
- degenerate solution
Answer: B
GATE ME 2016 Set 3, Question 65 (2 marks, NAT)
Industrial Engineering - Linear Programming
A firm uses a turning center, a milling center and a grinding machine to produce two parts. The table below provides the machining time required for each part and the maximum machining time available on each machine. The profit per unit on parts and are Rs. and Rs. respectively. The maximum profit per week of the firm is Rs. _______________

Answer: 39000 to 41000
GATE ME 2015 Set 3, Question 61 (2 marks, MCQ)
Industrial Engineering - Linear Programming
For the linear programming problem: The above problem has

- Unbounded solution
- Infeasible solution
- Alternative optimum solution
- Degenerate solution
Answer: A
GATE ME 2014 Set 3, Question 49 (2 marks, NAT)
Industrial Engineering - Linear Programming
Consider an objective function and the constraints The maximum value of the objective function is ________________.

Answer: 17 to 19
GATE ME 2013, Question 36 (2 marks, MCQ)
Industrial Engineering - Linear Programming
A linear programming problem is shown below. It has ..............

- an unbounded objective function
- exactly one optimal solution
- exactly two optimal solutions
- infinitely many optimal solutions
Answer: B
GATE ME 2011, Question 15 (2 marks, MCQ)
Industrial Engineering - Linear Programming
One unit of product requires of resource and of resource . One unit of product requires of resource and of resource . The profits per unit by selling product and are Rs. and Rs. respectively. The manufacturer has of resource and of resource . The unit worth of resource . i.e. dual price of resource in Rs. per is

Answer: A
GATE ME 2011, Question 16 (2 marks, MCQ)
Industrial Engineering - Linear Programming
One unit of product requires of resource and of resource . One unit of product requires of resource and of resource . The profits per unit by selling product and are Rs. and Rs. respectively. The manufacturer has of resource and of resource . The manufacturer can make a maximum profit of Rs.

Answer: B
GATE ME 2010, Question 3 (1 mark, MCQ)
Industrial Engineering - Linear Programming
Simplex method of solving linear programming problem uses
- all the points in the feasible region
- only the corner points of the feasible region
- intermediate points within the infeasible region
- only the interior points in the feasible region.
Answer: B
GATE ME 2009, Question 17 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Consider the following Linear Programming problem Maximize: Subject to

- The has a unique optimal solution.
- The is infeasible
- The is unbounded
- The has multiple optimal solutions.
Answer: D
GATE ME 2008, Question 18 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Consider the Linear programme Max + Subject to After introducing slack variables and , the initial basic feasible solution is represented by the table below (basic variables are and the objective function value is ). From this, one can conclude that

- The has a unique optimal solution
- The has an optimal solution that is not unique
- The is infeasible
- The is unbounded
Answer: B
GATE ME 2008, Question 19 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Consider the Linear programme Max + Subject to The dual for the is

Answer: A
GATE ME 2005, Question 20 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Consider a linear programming problem with two variables and two constraints. The objective function is: Maximize The corner points of the feasible region are and If an additional constraint is added, the optimal solution is

Answer: B
GATE ME 2005, Question 21 (2 marks, MCQ)
Industrial Engineering - Linear Programming
Consider a linear programming problem with two variables and two constraints. The objective function is: Maximize The corner points of the feasible region are and Let and be the decision variables of the dual and and be the slack variables of the dual of the given linear programming problem. The optimum dual variables are

- and
- and
- and
- and
Answer: A
GATE ME 2004, Question 22 (2 marks, MCQ)
Industrial Engineering - Linear Programming
A company produces two types of toys: and Production time of is twice that of and the company has a maximum of time units per day. The supply of raw material is just sufficient to produce toys (of any type) per day. Toy type requires an electric switch which is available @ pieces per day only. The company makes a profit of Rs. and Rs. on type and respectively. For maximization of profits, the daily production quantities of and toys should respectively be

Answer: C
GATE ME 2003, Question 23 (2 marks, MCQ)
Industrial Engineering - Linear Programming
A manufacturer produces two types of products, and at production levels of and respectively. The profit is given is The production constraints are The maximum profit which can meet the constraints is

Answer: A
GATE ME 2002, Question 24 (5 marks, NAT)
Industrial Engineering - Linear Programming
A furniture manufacturer produces chairs and tables. The wood-working department is capable of producing chairs or tables or any proportionate combinations of these per week. The weekly demand for chairs and tables is limited to and units respectively. The profit from a chair is Rs. and that from a table is Rs. Set up the problem as a Linear Program Determine the optimum product mix for maximizing the profit. What is the maximum profit? If the profit of each table drops to Rs.200 per unit, what is the optimal mix and profit?

GATE ME 2000, Question 25 (5 marks, TEXT)
Industrial Engineering - Linear Programming
Solve the following linear programming problem by simplex method What is the solution to the above problem? Add the constant to the simplex table of part and find the solution.

GATE ME 1996, Question 4 (1 mark, MCQ)
Industrial Engineering - Linear Programming
If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that
- Right hand side of the primal constraint can be altered without affecting the optimum solution
- Changing the right hand side of the primal constraint will disturb the optimum solution
- The objective function is unbounded
- The problem is degenerate
Answer: A