GATE ME 2006, Question 1 (2 marks, MCQ)

Industrial Engineering - Line Balancing

The table gives details of an assembly line. What is the line efficiency of the assembly line?

GATE ME 2006 question 1

Answer: C

GATE ME 2004, Question 2 (2 marks, MCQ)

Industrial Engineering - Line Balancing

An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce units during a regular -hour shift. This operation consists of three activities as below . For line balancing the number of work stations required for the activities and would respectively be

GATE ME 2004 question 2

Answer: A

GATE ME 1996, Question 3 (2 marks, MCQ)

Industrial Engineering - Line Balancing

In an assembly line for assembling toys, five workers are assigned tasks which take times of and minutes respectively. The balance delay for the line is

GATE ME 1996 question 3

Answer: C