GATE ME Inventory Control: Previous Year Questions

GATE ME (Mechanical Engineering) Inventory Control previous year questions from Industrial Engineering, with figures and the answer key.

Industrial Engineering | All GATE ME papers

GATE ME 2026, Question 37 (2 marks, NAT)

Industrial Engineering - Inventory Control

The inventory holding cost of an item is Rs. 0.50 per unit per month and the ordering cost per order is Rs. 550. A stockist needs to supply 10000 units of the item per year to the customers. Assume demand is fixed and shortage cost is infinite. Using classical economic order quantity (EOQ) model, the optimal lot size is units per order (rounded off to nearest integer).

GATE ME 2026 question 37

Answer: 1354

GATE ME 2025, Question 64 (2 marks, NAT)

Industrial Engineering - Inventory Control

A company uses 3000 units of a part annually. The units are priced as given in the table below. It costs Rs. 150 to place an order. Carrying costs are 40 percent of the purchase price per unit on an annual basis. The minimum total annual cost is Rs. ____________ (rounded off to 1 decimal place). Order quantity Unit price(Rs.) 1 to 499 500 to 999 1000 or more

GATE ME 2025 question 64

Answer: 26000 to 26100

GATE ME 2024, Question 38 (2 marks, MCQ)

Industrial Engineering - Inventory Control

A company orders gears in conditions identical to those considered in the economic order quantity (EOQ) model in inventory control. The annual demand is 8000 gears, the cost per order is 300 rupees, and the holding cost is 12 rupees per month per gear. The company uses an order size that is 25% more than the optimal order quantity determined by the EOQ model. The percentage change in the total cost of ordering and holding inventory from that associated with the optimal order quantity is

  1. 2.5
  2. 5
  3. 0
  4. 12.5

Answer: A

GATE ME 2023, Question 13 (1 mark, MCQ)

Industrial Engineering - Inventory Control

With reference to the Economic Order Quantity (EOQ) model, which one of the options given is correct?

GATE ME 2023 question 13

  1. Curve P1: Total cost, Curve P2: Holding cost, Curve P3: Setup cost, and Curve P4: Production cost.
  2. Curve P1: Holding cost, Curve P2: Setup cost, Curve P3: Production cost, and Curve P4: Total cost.
  3. Curve P1: Production cost, Curve P2: Holding cost, Curve P3: Total cost, and Curve P4: Setup cost.
  4. Curve P1: Total cost, Curve P2: Production cost, Curve P3: Holding cost, and Curve P4: Setup cost.

Answer: A

GATE ME 2022 Set 1, Question 22 (1 mark, MCQ)

Industrial Engineering - Inventory Control

Which one of the following is NOT a form of inventory?

  1. Raw materials
  2. Work-in-process materials
  3. Finished goods
  4. CNC Milling Machines

Answer: D

GATE ME 2022 Set 2, Question 33 (1 mark, NAT)

Industrial Engineering - Inventory Control

The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _______ parts (round off to the nearest integer).

Answer: 13 to 15

GATE ME 2021 Set 1, Question 30 (1 mark, NAT)

Industrial Engineering - Inventory Control

Q.20 RobotLtd.wishestomaintainenoughsafetystockduringthelead timeperiod betweenstartinganewproductionrunanditscompletionsuch thatthe probabilityofsatisfyingthecustomerdemandduringtheleadtimeperiodis 95%.Thelead timeperiod is 5 daysand daily customer demand can be assumed tofollow the Gaussian(normal) distributionwith mean50 units and a standard deviation of 10 units. Using Φ-1(0. 95) = 1. 64, where Φ represents the cumulative distribution function of the standard normal random variable, the amount of safety stock that must be maintained by Robot Ltd. to achieve this demand fulfillment probability for the lead time period is units (round off to two decimal places).

GATE ME 2021 Set 1 question 30

Answer: 331 to 333

GATE ME 2021 Set 2, Question 46 (2 marks, NAT)

Industrial Engineering - Inventory Control

Q.36 Dailyproduction capacity of a bearingmanufacturing company is 30000 bearings.Thedaily demand of thebearing is 15000.Theholdingcostperyear of keeping abearing in the inventory is20.The setup cost for the production of abatch is1800.Assuming300workingdays inayear,the economicbatch quantityinnumber of bearings is (in integer).

GATE ME 2021 Set 2 question 46

Answer: 40200 to 40300

GATE ME 2020 Set 1, Question 58 (2 marks, NAT)

Industrial Engineering - Inventory Control

Q.No.48 Considertwocasesasbelow. Case1:A company buys 1000pieces peryearof a certain partfromvendor‘X'. The changeover time is 2hours and thepriceis Rs.10per piece.Theholding cost rateperpart is10%peryear. Case2:Forthe same part,anothervendorY’offers a designwhere thechangeover time is6minutes,witha price ofRs.5per piece,anda holdingcost rateperpart of 100%peryear.The order size is 800pieces per year from‘X’and 200 pieces per year from'Y'. Assume the cost of downtime as Rs.200 per hour.The percentage reduction in the annualcostforCase2,as compared to Case1is (roundoffto2 decimal places).

GATE ME 2020 Set 1 question 58

Answer: 8.19 to 8.23

GATE ME 2020 Set 2, Question 57 (2 marks, NAT)

Industrial Engineering - Inventory Control

Q.No.47 per year.The replenishment is instantaneous and backorders (S units)per cycle areallowed asshowninthefigure. Inventory Time As soon as the quantity (Q units)ordered from the supplier is received,the backorderedquantityisissued to the customers.The ordering cost is Rs.300per order.The carrying cost is Rs.4per unit peryear.The cost of backorderingis Rs.25 per unit peryear.Based on the totalcostminimization criteria,themaximum inventoryreachedinthesystemis (roundoff tonearestinteger).

GATE ME 2020 Set 2 question 57

Answer: 1130 to 1140

GATE ME 2019 Set 2, Question 65 (2 marks, NAT)

Industrial Engineering - Inventory Control

Q.55 quantity is 400 valves per order. The holding cost is Rs. 24 per valve per year and the ordering cost is Rs. 400 per order.If the current order quantity is changed to Economic Order Quantity, then the saving in the total cost of inventory per year will be Rs. (round off to two decimal places). ENDOFTHEQUESTIONPAPER

GATE ME 2019 Set 2 question 65

Answer: 941 to 946

GATE ME 2018 Set 2, Question 28 (1 mark, MCQ)

Industrial Engineering - Inventory Control

Q.18 A local tyre distributor expects to sell approximately 9600 steel belted radial tyres next year. Annual carrying cost is Rs. 16 per tyre and ordering cost is Rs. 75. The economic order quantity of the tyres is (A) 64 (B) 212 (C) 300 (D) 1200

GATE ME 2018 Set 2 question 28

Answer: C

GATE ME 2016 Set 1, Question 64 (2 marks, NAT)

Industrial Engineering - Inventory Control

The annual demand for an item is units. The unit cost is Rs. and inventory carrying charges are of the unit cost per annum. The cost of one procurement is Rs. The time between two consecutive orders to meet the above demand is _______ month(s).

GATE ME 2016 Set 1 question 64

Answer: 1.9 to 2.1

GATE ME 2016 Set 2, Question 64 (2 marks, NAT)

Industrial Engineering - Inventory Control

A food processing company uses of corn flour every year. The quantity-discount price of corn flour is provided in the table below: The order processing charges are Rs. /order. The handling plus carry-over charge on an annual basis is of the purchase price of the corn flour per . The optimal order quantity (in ) is __________.

GATE ME 2016 Set 2 question 64

Answer: 1499 to 1501

GATE ME 2015 Set 2, Question 34 (1 mark, NAT)

Industrial Engineering - Inventory Control

Annual demand of a product is units and the ordering cost is Rs. per order. Considering the basic economic order quantity model, the economic order quantity is units. When the annual inventory cost is minimized, the annual inventory holding cost (in Rs.) is ___________

GATE ME 2015 Set 2 question 34

Answer: 34000 to 36000

GATE ME 2015 Set 3, Question 43 (2 marks, NAT)

Industrial Engineering - Inventory Control

The annual requirement of rivets at a ship manufacturing company is The rivets are supplied in units of 1 kg costing Rs. each. If it costs Rs. to place an order and the annual cost of carrying one unit is of its purchase cost, the cycle length of the order (in days) will be _______________

GATE ME 2015 Set 3 question 43

Answer: 76 to 78

GATE ME 2014 Set 2, Question 61 (2 marks, NAT)

Industrial Engineering - Inventory Control

Consider the following data with reference to elementary deterministic economic order quantity model The total number of economic orders per year to meet the annual demand is _______________.

GATE ME 2014 Set 2 question 61

Answer: 49 to 51

GATE ME 2014 Set 3, Question 61 (2 marks, MCQ)

Industrial Engineering - Inventory Control

A manufacturer can produce bearings per day. The manufacturer received an order of bearings per day from a customer. The cost of holding a bearing in stock is Rs. per month. Setup cost per production run in Rs. Assuming working days in a year, the frequency of production run should be

GATE ME 2014 Set 3 question 61

  1. days
  2. months
  3. days
  4. months

Answer: C

GATE ME 2014 Set 4, Question 29 (1 mark, NAT)

Industrial Engineering - Inventory Control

Demand during lead time with associated probabilities is shown below: Expected demand during lead time is ___________

GATE ME 2014 Set 4 question 29

Answer: 74 to 75

GATE ME 2011, Question 6 (1 mark, MCQ)

Industrial Engineering - Inventory Control

The word Kanban is most appropriately associated with

  1. economic order quantity
  2. just-in-time production
  3. capacity planning
  4. product design

Answer: B

GATE ME 2010, Question 20 (2 marks, MCQ)

Industrial Engineering - Inventory Control

Annual demand for window frames is Each frame costs Rs. and ordering cost is Rs. per order. Inventory holding cost is Rs. per frame per year. The supplier is willing to offer discount if the order quantity is or more, and if order quantity is or more. If the total cost is to be minimized, the retailer should

GATE ME 2010 question 20

  1. order frames every time
  2. accept discount
  3. accept discount
  4. order Economic Order Quantity

Answer: C

GATE ME 2009, Question 21 (2 marks, MCQ)

Industrial Engineering - Inventory Control

A company uses units of an item annually. Delivery lead time is days. The recorder point (in number of units) to achieve optimum inventory is

GATE ME 2009 question 21

Answer: C

GATE ME 2007, Question 22 (2 marks, MCQ)

Industrial Engineering - Inventory Control

The maximum level of inventory of item is and it is achieved with infinite replenishment rate. The inventory becomes zero over one and half month due to consumption at a uniform rate. This cycle continuous throughout the year. Ordering cost is Rs. per order and inventory carrying cost is Rs. per item per month. Annual cost (in Rs. ) of the plan, neglecting material cost, is

GATE ME 2007 question 22

Answer: D

GATE ME 2007, Question 23 (2 marks, MCQ)

Industrial Engineering - Inventory Control

In a machine shop, pins of diameter are produced at a rate of per month and the same is consumed at a rate of per month. The production and consumption continue simultaneously till the maximum inventory is reached. Then inventory is allowed to reduced to zero due to consumption. The lot size of production is If backlog is not allowed, the maximum inventory levels is

GATE ME 2007 question 23

Answer: B

GATE ME 2006, Question 24 (2 marks, MCQ)

Industrial Engineering - Inventory Control

Consider the following data for an item. Annual demand: units per year Ordering cost: Rs.100 per order Inventory holding rate: of unit price. The optimum order quantity (in units) is: Price quoted by a supplier The optimum order quantity (in units) is

GATE ME 2006 question 24

Answer: C

GATE ME 2006, Question 25 (2 marks, MCQ)

Industrial Engineering - Inventory Control

A stockist wishes to optimize the number of perishable items he needs to stock in any month in his store. The demand distribution for this perishable item is: The stockist pays Rs. for each item and he sells each at Rs. if the stock is left unsold in any month, he can sell the item at Rs. each. There is no penalty for unfulfilled demand. To maximize the expected profit, the optimal stock level is:

GATE ME 2006 question 25

  1. units
  2. units
  3. units
  4. units

Answer: B

GATE ME 2005, Question 26 (2 marks, MCQ)

Industrial Engineering - Inventory Control

The distribution of lead-time demand fro an item is as follows: The reorder level is times the expected value of the lead-time demand. The service level is

GATE ME 2005 question 26

Answer: C

GATE ME 2004, Question 27 (2 marks, MCQ)

Industrial Engineering - Inventory Control

There are two products P and Q with the following characteristics The economic order quantity (EOQ) of products P and Q will be in the ratio.

GATE ME 2004 question 27

Answer: C

GATE ME 2004, Question 28 (2 marks, MCQ)

Industrial Engineering - Inventory Control

A company has an annual demand of units, ordering cost of Rs./order and carrying cost of Rs./unit –year. If the stock-out costs are estimated to be nearly Rs. each time the company runs out-of-stock, the safety stock justified by the carrying cost will be

GATE ME 2004 question 28

Answer: C

GATE ME 2003, Question 29 (2 marks, MCQ)

Industrial Engineering - Inventory Control

Market demand for springs is per annum. A company purchases these springs in lots and sells them. The cost of making a purchase order is Rs. The cost of storage of springs is Rs. per stored piece per annum. The economic order quantity is

GATE ME 2003 question 29

Answer: C

GATE ME 2002, Question 7 (1 mark, MCQ)

Industrial Engineering - Inventory Control

An item can be purchased for Rs. The ordering cost is Rs. and the inventory carrying cost is of the item cost per annum. If the annual demand is 4000 units, the economic order quantity (in units) is

GATE ME 2002 question 7

Answer: D

GATE ME 2001, Question 33 (5 marks, TEXT)

Industrial Engineering - Inventory Control

A company is offered the following price breaks for order quantity Order cost is Rs. per order while the holding cost is of the purchase price. Determine the economic order quantity if the annual requirement is units.

GATE ME 2001 question 33

GATE ME 2000, Question 34 (5 marks, NAT)

Industrial Engineering - Inventory Control

A company places orders for supply of two items and The order cost for each of the items is Rs. /order. The inventory carrying cost is of the unit price per year per unit. The unit prices of the items are Rs. and Rs. respectively. The annual demands are and respectively. (a) Find the economic order quantities and the minimum total cost (b) A supplier is willing to give a discount on price, if both the items are ordered from him and if the order quantities for each item are units or more. Is it profitable to avail the discount?

GATE ME 2000 question 34

GATE ME 1999, Question 30 (2 marks, MCQ)

Industrial Engineering - Inventory Control

In computing Wilson’s economic lot size for an item, by mistake the demand rate estimate used was higher than the tree demand rate. Due to this error in the lot size computation, the total cost of setups plus inventory holding per unit time, would rise above the true optimum by approximately

GATE ME 1999 question 30

Answer: C

GATE ME 1998, Question 8 (1 mark, MCQ)

Industrial Engineering - Inventory Control

One of the following statements about (Periodic Reordering System) is not true. Identify.

GATE ME 1998 question 8

  1. requires continuous monitoring of inventory levels
  2. is useful in control of perishable items
  3. provides basis for adjustments to account for variations in demand
  4. In inventory holding costs are higher than in Fixed Recorder Quantity System

Answer: C

GATE ME 1998, Question 9 (1 mark, MCQ)

Industrial Engineering - Inventory Control

In inventory planning, extra inventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:

  1. Lot – for – lot production
  2. Economic Order Quantity lot size
  3. Period Order Quantity lot size
  4. Part Period total cost balancing

Answer: B

GATE ME 1997, Question 10 (1 mark, MCQ)

Industrial Engineering - Inventory Control

Setup costs do not include

  1. Labour cost of setting up machines
  2. Ordering cost of raw material
  3. Maintenance cost of the machines
  4. Cost of processing the work piece

Answer: B

GATE ME 1997, Question 35 (5 marks, TEXT)

Industrial Engineering - Inventory Control

Determine the number of production runs and also the total incremental cost in a factory for the data given below:

GATE ME 1997 question 35

GATE ME 1995, Question 11 (1 mark, MCQ)

Industrial Engineering - Inventory Control

If the demand for an item is doubled and the ordering cost halved, the economic order quantity

GATE ME 1995 question 11

  1. remains unchanged
  2. increases by a factor of
  3. is doubled
  4. is halved

Answer: A

GATE ME 1995, Question 36 (5 marks, TEXT)

Industrial Engineering - Inventory Control

Consider the following data for a product: Demand units/year Order cost Rs./order Holding cost of the unit cost / unit-year Unit cost Rs. (a) What is the economic order quantity? (b) Under the what is the number of annual orders? (c) With a policy of ordering every month what would be the total annual cost as a percentage of the cost at ?

GATE ME 1995 question 36

GATE ME 1991, Question 31 (2 marks, MCQ)

Industrial Engineering - Inventory Control

When the annual demand of a product is units, the (Economic Order Quantity) is units. If the annual demand is units the most appropriate will be

GATE ME 1991 question 31

  1. units
  2. units
  3. units
  4. units

Answer: C

GATE ME 1989, Question 32 (2 marks, MCQ)

Industrial Engineering - Inventory Control

In an ideal inventory control system, the economic lot size for a part is If the annual demand for the part is doubled, the new economic lot size required will be:

GATE ME 1989 question 32

Answer: D