GATE ME Forecasting: Previous Year Questions

GATE ME (Mechanical Engineering) Forecasting previous year questions from Industrial Engineering, with figures and the answer key.

Industrial Engineering | All GATE ME papers

GATE ME 2026, Question 36 (2 marks, NAT)

Industrial Engineering - Forecasting

The actual demand for castings in a factory is 500 units and 635 units for the months of January 2026 and February 2026, respectively. The forecasted demand for January 2026 is 250 units and smoothing constant is 0.7 . Using the exponential smoothing method, the forecast of the demand for castings in March 2026 is units (in integer).

GATE ME 2026 question 36

Answer: 572

GATE ME 2025, Question 37 (2 marks, MCQ)

Industrial Engineering - Forecasting

Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, are Period Actual demand Forecast

GATE ME 2025 question 37

  1. 0.8 and 42.0
  2. 0.8 and 4.2
  3. 8.0 and 42.0
  4. 8.0 and 4.2

Answer: B

GATE ME 2022 Set 2, Question 32 (1 mark, NAT)

Industrial Engineering - Forecasting

An electric car manufacturer underestimated the January sales of car by 20 units, while the actual sales was 120 units. If the manufacturer uses exponential smoothing method with a smoothing constant of α = 0.2, then the sales forecast for the month of February of the same year is ______ units (in integer).

Answer: 104

GATE ME 2021 Set 2, Question 53 (2 marks, NAT)

Industrial Engineering - Forecasting

Q.43 The demand and forecast of an item for five months are given in the table. Month Demand Forecast April 225 200 May 220 240 June 285 300 July 290 270 August 250 230 The Mean Absolute Percent Error (MAPE) in the forecast is % (round off to two decimal places)

GATE ME 2021 Set 2 question 53

Answer: 6 to 10

GATE ME 2020 Set 2, Question 43 (2 marks, MCQ)

Industrial Engineering - Forecasting

Q.No.33 3Theforecastforthemonthlydemandofaproductisgiveninthetablebelow. Month Forecast Actual Sales 1 32.00 30.00 2 31.80 32.00 3 31.82 30.00 Theforecast ismade byusing theexponential smoothingmethod.Theexponential smoothingcoefficient used inforecasting thedemandis (A) 0.10 (B) 0.40 (C) 0.50 (D) 1.00

GATE ME 2020 Set 2 question 43

Answer: A

GATE ME 2019 Set 1, Question 27 (1 mark, MCQ)

Industrial Engineering - Forecasting

Q.17 the demand-forecast of the product for the month of September is Month Demand January 450 February 440 March 460 April 510 May 520 June 495 July 475 August 560 (A) 490 (B) 510 (C) 530 (D) 536.67

GATE ME 2019 Set 1 question 27

Answer: B

GATE ME 2018 Set 1, Question 26 (1 mark, MCQ)

Industrial Engineering - Forecasting

Q.16 The time series forecasting method that gives equal weightage to each of the m most recent observations is (A) Moving average method (B) Exponential smoothing with linear trend (C) Triple Exponential smoothing (D) Kalman Filter

GATE ME 2018 Set 1 question 26

Answer: A

GATE ME 2016 Set 3, Question 64 (2 marks, MCQ)

Industrial Engineering - Forecasting

The demand for a two-wheeler was units and units in April and May respectively. The forecast for the month of April was units. Considering a smoothing constant of the forecast for the month of June is

GATE ME 2016 Set 3 question 64

  1. units
  2. units
  3. units
  4. units

Answer: D

GATE ME 2015 Set 1, Question 44 (2 marks, NAT)

Industrial Engineering - Forecasting

For a canteen, the actual demand for disposable cups was units in January and units in February. The forecast for the month of January was units. The forecast for the month of March considering smoothing coefficient as is_______________

GATE ME 2015 Set 1 question 44

Answer: 568 to 570

GATE ME 2015 Set 2, Question 35 (1 mark, MCQ)

Industrial Engineering - Forecasting

Sales data of a product is given in the following table: Regarding forecast for the month of June, which one of the following statements is TRUE?

GATE ME 2015 Set 2 question 35

  1. Moving average will forecast a higher value compared to regression.
  2. Higher the value of order the greater will be the forecast value by moving average.
  3. Exponential smoothing will forecast a higher value compared to regression.
  4. Regression will forecast a higher value compared to moving average.

Answer: D

GATE ME 2014 Set 1, Question 29 (1 mark, MCQ)

Industrial Engineering - Forecasting

In exponential smoothening method, which one of the following is true?

  1. and high value of is used for stable demand
  2. and high value of is used for unstable demand
  3. and high value of is used for stable demand
  4. and high value of is used for unstable demand

Answer: B

GATE ME 2014 Set 3, Question 29 (1 mark, NAT)

Industrial Engineering - Forecasting

The actual sales of a product in different months of a particular year are given below: The forecast of the sales, using the 4-month moving average method, for the month of February is ____________.

GATE ME 2014 Set 3 question 29

Answer: 239 to 241

GATE ME 2013, Question 14 (1 mark, MCQ)

Industrial Engineering - Forecasting

In simple exponential smoothing forecasting, to give higher weightage to recent demand information, the smoothing constant must be close to

  1. zero

Answer: D

GATE ME 2010, Question 16 (2 marks, MCQ)

Industrial Engineering - Forecasting

The demand and forecast for February are and respectively. Using single exponential smoothening method (smoothening coefficient ), forecast for the month of March is

GATE ME 2010 question 16

Answer: C

GATE ME 2009, Question 6 (1 mark, MCQ)

Industrial Engineering - Forecasting

Which of the following forecasting methods takes a fraction of forecast error into account for the next period forecast?

  1. simple average method
  2. moving average method
  3. weighted moving average method
  4. exponential smoothing method

Answer: D

GATE ME 2008, Question 17 (2 marks, MCQ)

Industrial Engineering - Forecasting

A moving average system is used for forecasting weekly demand. and are sequences of forecasts with parameters and , respectively, where and denote the numbers of weeks over which the moving averages are taken. The actual demand shows a step increase from to at a certain time. Subsequently,

GATE ME 2008 question 17

  1. neither nor will catch up with the value
  2. both sequences and will reach in the same period
  3. will attain the value
  4. will attain the value

Answer: D

GATE ME 2005, Question 18 (2 marks, MCQ)

Industrial Engineering - Forecasting

The sales of a product during the last four years were and units. The forecast for the fourth year was units. If the forecast for the fifth year, using simple exponential smoothing, is equal to the forecast using a three period moving average, the value of the exponential smoothing constant is

GATE ME 2005 question 18

Answer: C

GATE ME 2004, Question 7 (1 mark, MCQ)

Industrial Engineering - Forecasting

For a product, the forecast and the actual sales for December were and respectively. If the exponential smoothing constant is taken as then forecast sales for January would be

GATE ME 2004 question 7

Answer: C

GATE ME 2003, Question 19 (2 marks, MCQ)

Industrial Engineering - Forecasting

The sale of cycles in a shop in four consecutive months are given as Exponentially smoothing average method with a smoothing factor of is used in forecasting. The expected number of sales in the next month is

GATE ME 2003 question 19

Answer: B

GATE ME 2002, Question 8 (1 mark, MCQ)

Industrial Engineering - Forecasting

A regression model is used to express a variable as a function of another variable this implies that

GATE ME 2002 question 8

  1. There is a causal relationship between and
  2. A value of may be used to estimate a value of
  3. Values of exactly determine values of
  4. There is no causal relationship between and

Answer: B

GATE ME 2001, Question 9 (1 mark, MCQ)

Industrial Engineering - Forecasting

When using a simple moving average to forecast demand, one would

  1. give equal weight to all demand data
  2. assign more weight to the recent demand data
  3. include new demand data in the average without discarding the earlier data
  4. include new demand data in the average after discarding some of the earlier demand data

Answer: A

GATE ME 2000, Question 20 (2 marks, MCQ)

Industrial Engineering - Forecasting

In a time series forecasting model, the demand for five time periods was and A linear regression fit resulted in an equation where is the forecast for period . The sum of absolute deviations for the five data is

GATE ME 2000 question 20

Answer: A

GATE ME 1998, Question 10 (1 mark, MCQ)

Industrial Engineering - Forecasting

Which one of the following forecasting techniques is not suited for making forecasts for planning production schedules in the short range?

  1. Moving average
  2. Exponential moving average
  3. Regression analysis
  4. Delphi

Answer: D

GATE ME 1997, Question 11 (1 mark, MCQ)

Industrial Engineering - Forecasting

The most commonly used criteria for measuring forecast error is

  1. Mean absolute deviation
  2. Mean absolute percentage error
  3. Mean standard error
  4. Mean square error

Answer: A

GATE ME 1997, Question 21 (2 marks, MCQ)

Industrial Engineering - Forecasting

In a forecasting model, at the end of period the forecasted value for period is Actual value in the periods to are constant at . if the assumed simple exponential smoothing parameter is then the at the end of period is

GATE ME 1997 question 21

Answer: B

GATE ME 1989, Question 22 (2 marks, MCQ)

Industrial Engineering - Forecasting

Which of the following is a technique for forecasting?

  1. Exponential smoothing
  2. Gantt chart technique
  3. Control charts

Answer: A