GATE ME Assignment: Previous Year Questions

GATE ME (Mechanical Engineering) Assignment previous year questions from Industrial Engineering, with figures and the answer key.

Industrial Engineering | All GATE ME papers

GATE ME 2022 Set 1, Question 58 (2 marks, NAT)

Industrial Engineering - Assignment

An assignment problem is solved to minimize the total processing time of four jobs (1, 2, 3 and 4) on four different machines such that each job is processed exactly by one machine and each machine processes exactly one job. The minimum total processing time is found to be 500 minutes. Due to a change in design, the processing time of Job 4 on each machine has increased by 20 minutes. The revised minimum total processing time will be ________ minutes (in integer).

Answer: 520

GATE ME 2019 Set 1, Question 64 (2 marks, NAT)

Industrial Engineering - Assignment

Q.54 to any of the five different machines (M1, M2, M3, M4 and M5). The time durations taken (in minutes) by the machines for each of the jobs, are given in the table. However, each job is assigned to a specific machine in such a way that the total processing time is minimum. The total processing time is minutes. M1 M2 M3 M4 M5 J1 40 30 50 50 58 J2 26 38 60 26 38 J3 40 34 28 24 30 J4 28 40 40 32 48 J5 28 32 38 22 44

GATE ME 2019 Set 1 question 64

Answer: 146

GATE ME 2014, Question 1 (1 mark, MCQ)

Industrial Engineering - Assignment

The total number of decision variables in the objective function of an assignment problem of size ( jobs and machines) is

GATE ME 2014 question 1

Answer: A

GATE ME 2014 Set 4, Question 28 (1 mark, MCQ)

Industrial Engineering - Assignment

Q.18 The total number of decision variables in the objective function of an assignment problem of size (A) 𝑛𝑛2 n × n (n jobs and n machines) is (B) 2𝑛𝑛 (C) 2𝑛𝑛−1 (D) 𝑛𝑛 ME04 (GATE 2014)

GATE ME 2014 Set 4 question 28

Answer: A

GATE ME 2006, Question 3 (2 marks, MCQ)

Industrial Engineering - Assignment

A firm is required to procure three items and The prices quoted for these items (in Rs.) by suppliers and are given in table. The management policy requires that each item has to be supplied by only one supplier and one supplier supply only one item. The minimum total cost (in Rs.) of procurement to the firm is:

GATE ME 2006 question 3

Answer: C